CSC RENOVATION - SUMMER 2021

The CSC is undergoing a major transformation this summer, and we cannot be more excited! We also cannot be more thankful to all of the people who made this possible, most especially all of the individuals whose support makes these renovations possible.

A committee composed of CSC staff, students, and community members, supported by strong partnerships with KRJ Architecture, Lawlor Corporation and CI Select, have prepared us to achieve our goal:  To establish a state-of-the art facility for students and community members that fosters and promotes their spiritual growth and development, and supports the mission of the CSC.

Our renovation features:

  • Intentionally-designed space to support identified programming and student preferred use.

  • Structural modifications to establish an inviting primary building entrance.

  • New welcome center.

  • New family restroom.

  • Updated furnishings/fixtures and select refurbishment in our Music, Dining and Living Rooms, as well as the Library and Social Hall.

  • A new kitchen with serving counter.

  • Updated audiovisual throughout the facility.

  • Canopy over existing courtyard.

Total project cost is $1.5M and will be financed by a combination of capital campaign funds, savings, and a loan from the Archdiocese. 

Week 10
Week 9
Week 8
Week 7
Week 6
Week 5
 
Week 4
Demolition and deconstruction continues in the CSC House, Social Hall, Library and Kitchen.
Week 3
Demolition and deconstruction continues in the CSC House, Social Hall, Library and Kitchen.
Week 2
Demolition has started in all of the spaces we are renovating this summer.
Week 1
The renovation commenced on Monday, May 17.  The focus over the next few weeks will be demolition! 
Pre-Construction: Renovation Blessing
On May 16, Fr. Gary blessed the renovation and everyone who is a part of it. He then made the ceremonial groundbreaking in the dinning room.